Grain Belt Express filed its fourth petition for condemnation in Callaway County last week for an easement to install electric transmission lines.
The lawsuit was filed Friday against Auxvasse resident Dustin Hudson, who is refusing to allow the project to use the land.
TOPEKA — The Grain Belt Express, an 800-mile electric transmission line to be built through Kansas, Missouri, Illinois and Indiana, announced $1.7 billion in contractor awards on Wednesday. The awards ...
The U.S. Energy Dept. has withdrawn a $4.9-billion conditional loan guarantee for Invenergy’s Grain Belt Express transmission line, claiming financial shortcomings that officials determined were ...
Grain Belt Express has filed nearly 40 eminent domain petitions against Missouri property owners since 2021 as it prepares to build a transmission line across the state. The first eminent domain ...
This is an archived article and the information in the article may be outdated. Please look at the time stamp on the story to see when it was last updated. MOBERLY, Mo. – The Missouri Public Service ...
Invenergy announced May 7 that the Grain Belt Express, the largest electric transmission project in the United States, was awarding nearly $1.7 billion in combined U.S. contractor awards to Quanta ...
Highest Capacity and First U.S. Transmission Line to Connect Four Grid Regions Builds on Domestic Energy Supply Chain and Manufacturing Investments "We're pleased to partner with Quanta and Kiewit as ...
Grain Belt Express has filed nearly 40 eminent domain petitions against Missouri property owners since 2021 as it prepares to build a transmission line across the state. The first eminent domain ...
Grain Belt Express has filed its first petition for condemnation in Callaway County for an easement to install electric transmission lines. Grain Belt Express filed a petition for condemnation Jan. 21 ...